There are
many types of contracts that can be used to accomplish the small to medium
sized maintenance & repair jobs that facility owners face every day. The
following table illustrates the best use for each of the different types of
contracts. Click on the contract for a synopsis.
|
Contract Type |
Best Use |
Pros |
Cons |
Project Size |
|
JOC – Job Order Contact |
Multi-traded small to medium sized maintenance, repair and minor new construction. |
Saves considerable time, money and improves quality. |
Must use a pre-priced book of construction
tasks. Off the shelf estimating guides are not appropriate. |
$5,000 to $1,000,000 |
|
SABER – Simplified Acquisition of Base Engineering Requirements |
Multi-traded small to medium sized maintenance, repair and minor new construction. |
Saves considerable time, money and improves quality. |
Must use a pre-priced book of construction tasks.
Off the shelf estimating guides are not appropriate. |
$5,000 to $1,000,000 |
|
TOC - Task Order Contract |
Multi-traded small to medium sized maintenance, repair and minor new construction. |
Saves considerable time. |
More expensive than other methods. |
$5,000 to $1,000,000 |
|
Term/Requirements Contract |
Single traded small to medium sized new construction. |
Saves considerable time and money. |
Unbalanced bidding and tasks often occur outside of original scope.
Administrative burden verifying installed quantities. |
< $100,000 |
|
SOC – Solution Order Contract |
Medium new construction. |
Faster than traditional design-build and design-bid-build. |
More expensive than most other contract methods. |
> $1,000,000 |
|
MATOC – Multiple Award Task Order Contract |
Medium new construction. |
Faster than traditional design-build and design-bid-build. |
More expensive than most other contract methods. |
> $1,000,000 |
|
Design-Bid-Build |
Large New Construction |
Comprehensive design prior to construction. |
Extremely slow process. Changes and claims are common. |
> $1,000,000 |
|
Design-Build |
Medium to large new construction projects. |
Faster than design-bid-build and promotes innovation. Shifts more risk to contractor. |
Few when award is based on Best Value or Qualifications. |
> $1,000,000 |
|
Contractor at Risk |
Medium to large new construction projects |
Faster than design-bid-build. Shifts financial risk to contractor. |
Expensive. Contracts typically have loopholes allowing contractors to reduce risk. |
> $1,000,000 |
Job Order Contract (JOC)
JOC is a firm
fixed-price indefinite quantity contract which contains an extensive database
of priced construction & construction related tasks. Job Orders issued
under a master contract are priced using the tasks from the database. JOC saves
on costs from project procurement to construction. Jobs are jointly scoped by
the facility owner and the contractor eliminating the need for costly bid
documents. The joint scope virtually eliminates changes and claims.
Construction typically starts within weeks of a project being identified
compared to months under traditional systems. The contractor receives future
job orders based on the facility owner’s satisfaction with current job orders
thus ensuring high quality work.
Simplified Acquisition of Base Engineering Requirements (SABER)
SABER is
the Air Force’s version of JOC.
Task Order Contract (TOC)
TOC is a
multiple award construction contract. Each order under the contract is
competitively bid among pre-selected firms. The pre-selected contractors must
prepare a proposal for each and every job. This increases the contractor’s overhead and therefore the cost to
facility owner is higher than a JOC or SABER
Term/Requirement Contract
A term
contract is typically a single trade contract where the facility owner lists
items that they want to accomplish and the anticipated quantities. The
contractor bids the unit prices for each of the items. These contracts are
notorious for unbalanced bidding. The contractor often seems to know
anticipated quantities better than the facility owner and uses that to their
advantage. These contracts are also problematic when work must be accomplished
that is not listed as one of the items.
Solution Order Contract (SOC)
SOC is a
multiple award design-build contract. Each order under the contract is
competitively bid among pre-selected firms. The best “solution” for each order
wins. This is a very expensive approach to construction. Each of the
pre-selected firms must prepare a solution for each order. This often involves
design and engineering. The facility owner is paying for redundant design and
engineering on each order for as many pre-selected firms they have under
contract.
Multiple Award Task Order Contract
(MATOC)
MATOC is
very similar to SOC.
Design-Bid-Build
Design-Bid-Build
is the traditional method of construction contracting whereby a project is
designed (in-house or by outside firm), advertised for bid, and contracted to
the low bidder. This method of construction has its place with the large new
construction projects but is too costly and time consuming for the small to
medium sized projects. Change orders and claims are common with this process.
Design-Build
Design-Build
is a single contract for both the design and construction based on design
criteria set by the facility owner. This method of construction shifts some of
the risk to the contractor and expedites the construction process. It allows
the contractor flexibility for innovation in all aspects of the design
construction process. Change orders and claims are reduced with this process.
Contractor at Risk (CM at Risk)
CM at Risk is a contract under which a
contractor guarantees a maximum fixed price and is at risk if the price goes
above that. Contractors are typically involved in the design and engineering
stages of a project to help them minimize their risk. CM at risk is generally
used on large capital projects where budgets must not be exceeded. It is not
appropriate for small to medium size projects where risk is minimal to start
with. The transfer of risk comes at a price. The CM at risk contracts are
generally more expensive than other contracting methods.
For CM at risk contracts that are based on a percent of construction, there are
no incentives to keep costs under control.